East Tunnel Project, B-2 South Parking Lot

Author: Department of Facilities Design & Operations

East Tunnel Project: Parts of the B-2 South Lot, near the Wellness Center, will be affected while the fenced-off construction zone is changed close to the two new residence halls.
 

Phase 1: (Monday, June 15 through Monday, June 29) ADA Parking will be temporarily moved to the north side of the parking lot, near Holy Cross Drive. A temporary walkway will be constructed for pedestrians to access campus sidewalks as well.
View map of the project site.

Phase 2: (Monday, June 29 through Wednesday, July 1) A new walkway will be available along the western length of the parking lot. ADA Parking will move back to the western corner of the lot. A temporary walkway will be constructed for pedestrians to access campus sidewalks while the fenced-off construction zone is relocated along Holy Cross Drive.
View map of the project site.